Project Timeline

June

2024

Interior renovation begins at 800 A Street.

May

2024

Derelict house at 802 A Street is demolished. Space will become part of our client/patient parking lot. 

April

2024

Interior demolition begins at 800 A Street on April 22nd.

January

2024

Groundbreaking ceremony on January 25th celebrated the start of construction.

June

2023

Building permits submitted to Marin County for construction of new health center.

April 3

2023

Purchase of new building completed. Ritter Center takes ownership of 800 A Street.

August 9

2022

City Planning Commission approved the conditional use permit for 800 A Street.